CREATE,located at NUS University Town, Singapore project was completed in mid year 2011.
PowerQ was involved in this project from late year 2010 to mid 2011 and our scope comprised of base build system and equipments serving the research facilities. We had tested and commissioned more than 200 mechanical equipment which are controlled and monitored by Central System.
The T&C was performed under the general supervision and direction of the M&E Contractor and Consultants. For the post greenfield project during year 2012, PowerQ had commissioned several BSL labs including reliability test for various system such as CDA, Gasses, Vacuum, Electrical, Fire, BMS, DCP CHW and ACMV.