The Marina Bay Sands (MBS ) Singapore www.marinabaysands.com is developed by one of the world’s biggest entertainment companies, Las Vegas Sands, at Marina Bay waterfront in central Singapore. We are perform the T&C work to MBS representative satisfaction under the general supervision and direction of the MBS, Consultants and our clients.
December 9, 2008 – 8:39 pm
PowerQ Technology Pte Ltd is proud to formally unveil its new brand identity designed by renowned design company Trevue Innovations.
November 15, 2008 – 3:13 am
Murata electronics plant had an incident where a water pipe had leaked in the Process area. The owner took a proactive approach to investigate the condition of piping and had requested TKS to conduct necessary investigation and audit to check integrity of the system. PowerQ was called upon to assist TKS to inspect the length [...]
November 15, 2008 – 2:55 am
Lexmark, a printer system manufacturer, required an independent 3rd Party survey and audit of their fire sprinkler system for the Lexmark Electronics Facility –Cebu Philippines. The fire sprinkler system was surveyed, and results recorded. A comparison of compliance to NFPA Codes, specifically NFPA 13 and 20, was used as a basis for ascertaining the degree [...]
November 15, 2008 – 1:26 am
excerpts from Appreciation letter from GSK Biologiocals Singapore to PowerQ dated 28 Feb 2010
“PowerQ Team has been consistant in their support for project with their expertise,it was often necessary for weekend and overnight works to meet projects tight commissioing and qualification schedule.”
November 14, 2008 – 2:46 am
PowerQ delivered on time and did a commendable job on the Most Prestigious, Singapore project. The HVAC system was redesigned as per the requirements and all the work was completed with very little downtime.
Project Director,
Most Prestigious Group
November 13, 2008 – 11:26 pm
PowerQ successfully completes the commissioning of GSK Biologicals VaccinePlant, Singapore
November 10, 2008 – 7:07 am
PowerQ performed power measurements on Switch Boards to determine the sufficient margin of capacity for a future upgrade.
The power monitoring was conducted at Main Switchboard and SSB. The measurement was conducted using power quality monitor Fluke 434. The objective of the work was to carry out a power measurement with a view to determine the [...]
November 10, 2008 – 6:59 am
The Dubai Mall is the one of largest malls in the world being built in UAE by Emaar Properties. The mall is a part of ’Downtown Dubai’. PowerQ was engaged by consultants to analyse and study the potential impact of strong electromagnetic field generated by the transformers, associated power cables, bus-ducts and switchgear.
In large commercial [...]
November 10, 2008 – 6:57 am
In order to ensure adequate distribution of electrical load to new and existing tenants, the building management had asked contractor M/s Kurihara to confirm that the electrical system installed by them was not contributing to excessive harmonics distortion. Kurihara engaged PowerQ to undertake the monitoring of the 3 Main Switchboards supplying power to to a [...]